Ameresco to get 2.1GWh BESS project for Southern California Edison to ‘substantial completion by summer’

Renewable energy and energy efficiency company Ameresco has nearly completed its three-site, 2.1GWh battery energy storage system (BESS) project for utility Southern California Edison (SCE).

In announcing its most recent quarterly financial results, the company offered an update to what is considered one of the largest utility-led BESS construction contracts seen in the US to date.

System integrator FlexGen has been hired to work on the project including inverter and software integration, although not battery storage supply.

Having said last August that both Ameresco and SCE’s teams were “working round the clock” to get those projects done, by the end of 2022, they were about 95% completed, chief financial officer (CFO) Doran Hole said in an earnings conference call.