Zambia Increases Load-Shedding To 12 Hours a Day!

January 4, 2023

The water levels in Kariba Dam are dangerously low, mainly due to climate change-induced irregular rainfall patterns. The dam is shared between Zambia and Zimbabwe. The dam hosts hydropower generation plants for both countries. The installed generation capacity on the Zimbabwe side is 1,050 MW. On the Zambian side, the installed generation capacity is 1080 MW.

In December of last year, the Zambezi River Authority (ZRA), the body that manages and regulates water usage at the Kariba Dam, announced that the water levels in the dam were now dangerously low. The ZRA issued a statement saying it had directed the two power companies, ZESCO in Zambia and ZPC in Zimbabwe, to reduce generation at Kariba. ZESCO Limited on the Zambian side was asked to reduce generation at the Kariba North Bank Power Station to 800 MW maximum. ZRA directed Zimbabwe Power Company (Link) reduce power generation to a maximum of 300 MW.

Read More on CleanTechnica